Marikana Property AD Hoc Maintenance Electrical works

Area: Marikana Property

Date: 22 Jan 2026

Duration: From Jan 2026 to Dec 2030.

Project Description: Maintaining Marikana properties (All electrical work and plumbing work)

Pyromet Thermocouples Installation

Area: Smelter

Date: March 2023 to April 2023

Project Description: Decommissioning and disconnecting. Stripping off old meshwire racks, ethernet cables, old junction boxes, and CCG boxes. Fabrication and installation of new panel frames, installation of new meshwire racks, installation of new ethernet cables, installation of new CCG boxes, glanding, termination, and commissioning. 

Conveyor Pulling Monitor

Area: Smelter

Date: Start Sep 2024 to Nov 2024

Project Description: Fabrication and installation of panel frames, installation of meshwire racks, installation of ethernet cables, 2-pair cables, and electrical cables to power the panels. Glandinng, termination, and commissioning.

Ventilation System

Area: BMR & PGM

Date: Start Sep 2024 to Nov 2024

Project Description: Installation of air system ventilation. Installation of the air cooler blower fan. Installation of the extraction fan.Installation of square and round ducting.

We have the experience because we've done the work